Economy

Stage 6 Load Shedding Renews Debate Over Eskom’s Reliability

2 Mins Read
Email :

Economy/ 24 February 2025, 09:40am/ Lijeng Moruthane

Load shedding leaves parts of Johannesburg without power as Stage 6 disruptions continue: Image Supplied

By Lijeng Moruthane: The sudden return of Stage 6 load shedding has ignited a political firestorm, with opposition parties, trade unions, and citizens slamming the government and Eskom for failing to maintain a stable electricity supply.

The Democratic Alliance (DA) has criticized what it calls an “over-reliance” on Eskom, warning that South Africa’s power crisis will persist as long as the government maintains a monopoly over energy generation.

“Eskom has proven time and time again that it cannot be the country’s primary energy supplier. The failure to diversify generation capacity has left South Africa vulnerable to blackouts,” said DA spokesperson on electricity and energy Kevin Mileham. “We need urgent reforms to open up the sector and reduce dependence on a single entity that is clearly failing.”

Trade unions have also voiced frustration. South African Federation of Trade Unions (SAFTU) General Secretary Zwelinzima Vavi labeled the return of load shedding as “disgusting,” arguing that it reflects decades of mismanagement.

“We are in the 31st year of democracy, yet we are still dealing with the same electricity crisis. This comes after the National Energy Regulator of SA granted Eskom a tariff increase. How do you charge people more for a service you cannot provide?” Vavi said.

The Economic Freedom Fighters (EFF) also condemned the government, accusing it of failing to resolve the crisis despite repeated promises.

Eskom escalated load shedding to Stage 6 at 1:30 AM on Sunday after 10 generating units failed at three power stations. The crisis was further compounded by the utility’s own recovery plan, which had already taken 7,500 megawatts offline for maintenance.

Electricity Minister Dr. Kgosientsho Ramokgopa admitted that the aggressive maintenance approach left little room to absorb unexpected failures.

“The headroom we created for maintenance did not give us enough flexibility to handle multiple unit failures. When that happens, the only tool at our disposal is load shedding, and unfortunately, that risk has materialized,” Ramokgopa said.

Eskom Board Chairperson Mteto Nyati apologized to South Africans, saying the board was “very disappointed” to have to implement such drastic power cuts.

“This is not where we wanted to be. We sincerely apologize for the return of Stage 6 load shedding,” Nyati said during a media briefing.