Free State/ 03 March 2026, 16:34pm/ Mpho Mokoena

Matjhabeng Executive Mayor Cllr Thanduxolo Khalipha: Image Supplied

By Mpho Mokoena: After years of frustration over overflowing manholes, foul odours and repeated spillages, residents of Naudeville (Ward 33) are set to get long-awaited relief following the official launch of a major sewer infrastructure rehabilitation project by Matjhabeng Local Municipality.

Executive Mayor Cllr Thanduxolo Khalipha unveiled the R52 million intervention—a 24-month programme designed to repair, unblock and rehabilitate a sewer network officials say is severely dilapidated in places, contributing to recurring sewage spillages in affected streets.

Speaking to community members alongside Members of the Mayoral Committee (MMCs), the ward councillor and senior municipal leadership, Khalipha framed the project as both a public health response and a restoration of dignity.

“This is not a cosmetic project. It is a dignity project,” Khalipha said. “No family should live with sewage running past their gate, no child should walk to school through contaminated streets, and no community should be made to feel forgotten because infrastructure has failed.”

For many residents, sewer blockages have become an exhausting cycle: spills, temporary unblocking, and then the same problem again. The municipality says this rehabilitation initiative is intended to break that cycle by addressing root causes, including damaged pipe sections, chronic blockage points and broader network degradation.

The scope of work includes: repairing and unblocking existing sewer lines; and rehabilitating infrastructure so deteriorated that it has repeatedly triggered spillages.

Municipal officials said the project’s objective is clear: clean, safe, sewer-free streets—and a sewer system residents can rely on over the long term.

“We are investing so that the solution lasts,” Khalipha said. “Residents deserve a sewer system that works every day—not only on the day the truck arrives.”

Beyond the engineering work, the municipality said the project will also support local economic activity. Thirty local labourers, including subcontractors, are expected to benefit directly through employment and enterprise opportunities linked to the rehabilitation work.

“Infrastructure must also put bread on the table,” the mayor said. “This project is designed to improve living conditions while creating real opportunities for local workers and small contractors.”

The implementing agent, VCW, has been appointed to oversee execution and ensure quality control, compliance with standards and on-time delivery. During the launch, the municipality also introduced the contractor and consultant to the community, describing the move as an early commitment to transparency.

“We are putting names and faces to this work from day one,” Khalipha added. “When communities know who is responsible, accountability becomes real—and performance improves.”

Sewer spillages are more than an inconvenience; they can pose serious health and environmental risks, particularly where contaminated water collects near homes, footpaths and open ground. Municipal officials said the rehabilitation project forms part of Matjhabeng’s broader commitment to protecting public health and improving living conditions.

“When sewer systems collapse, it is the poorest households who suffer first and longest,” Khalipha said. “We are here to correct that—decisively and permanently.”

As construction progresses, residents have been urged to remain engaged, report faults promptly and cooperate with site teams where access to sections of the network may be required.

Leave a Reply