Mpumalanga’s R2 Billion Fresh Produce Market Failures Expose Poor Planning

3 Mins Read
Email :

Mpumalanga/ 03 December 2024, 14:30pm/ Lijeng Moruthane

Mpumalanga International Fresh Produce Market remains inoperable after six years, with no running water or electricity, despite a R2 billion investment from the provincial government: Image Supplied

By Lijeng Moruthane: The ongoing failures of the R2 billion Mpumalanga International Fresh Produce Market have highlighted alarming levels of poor planning and mismanagement within the provincial government, according to the Democratic Alliance (DA).

Despite six years of development and a massive financial investment, the market remains inoperable, still lacking basic services such as running water and electricity.

The DA has condemned the delays as a clear indication of the ANC-led government’s inability to manage large-scale projects and deliver on promises made to the province’s farmers and agribusinesses.

Tersia Marshall, DA Spokesperson for Agriculture, Rural Development, Land and Environmental Affairs, expressed outrage over the ongoing mismanagement, saying the project’s failures are an embarrassment to the people of Mpumalanga.

“The failures on this R2 billion project are a shocking indication of the poor planning and mismanagement which the ANC government in Mpumalanga continues to deliver,” Marshall said.

“After six years and a budget of over R2 billion, this facility is still not operational, leaving local farmers without the support they desperately need.”

The DA also pointed to the Department of Agriculture’s failure to pay utility bills to the City of Mbombela, resulting in the disconnection of the market’s electricity supply.

This, they argue, is a glaring example of neglect, highlighting the lack of responsibility and oversight in the handling of public funds. “The neglect of basic obligations, such as ensuring the market has access to electricity and running water, is not only irresponsible, it’s unacceptable,” Marshall said.

“How can a R2 billion facility, which was supposed to drive economic growth and support local agriculture, be left in such a state of disrepair?”

The market was intended to be a key player in boosting the province’s agricultural sector, offering support to local farmers and stimulating the fresh produce value chain.

However, the DA warns that the continued failures are not just disappointing but potentially devastating for the region’s farmers.

“The government has failed to provide the infrastructure needed to make this market operational. Instead of creating opportunities for economic growth, they have wasted taxpayer money and left farmers in limbo,” Marshall concluded.

With the project continuing to stall, the DA has called on Premier Mandla Ndlovu to take immediate action to resolve the issues and ensure the market is fully operational, warning that if the current administration cannot get the project back on track, they will hold them accountable.