By Mpho Mokoena: The Fezile Dabi District Municipality has issued a detailed response to a City Press article published on March 9, 2025, which alleged mismanagement surrounding a critical borehole project aimed at alleviating water shortages in the Tweeling and Mafahlaneng communities. The municipality aims to clarify the facts and address the concerns raised.
According to municipal officials, the project, awarded on July 31, 2024, involves drilling 12 boreholes, with 9 currently equipped and reported as 91% complete. This initiative is particularly crucial given the anticipated challenges posed by the impending Lesotho Water Highlands Tunnel Closure, which is expected to exacerbate existing water distribution issues.
The total cost of the project is stated to be R6.4 million, as per the tender documentation. The municipality highlighted several significant milestones achieved as of March 7, 2025:
Site establishment: 100% complete
Drilling of boreholes: 100% complete, including geohydrology and site assessments
Pump-houses: 100% complete, including all necessary fittings and control panels
Manholes: 100% complete
Pipeline: 100% complete
Borehole ancillaries: 100% complete
Electrical installations: 100% complete, including poles, MV lines, and transformer installation
The municipality refuted claims of financial instability, emphasizing that recent audits conducted by the Auditor General of South Africa did not raise concerns regarding its financial sustainability. It also addressed the allegation that the tender was awarded without identifying the locations for the boreholes, clarifying that the locations of the project were explicitly indicated, along with the coordinates for each borehole.
Regarding allegations of fraud and claims against Municipal Manager Sipho Thomas, the municipality stated that the matter had been addressed in a council meeting on October 28, 2024. Further clarification was provided by the University of Fort Hare and the Office of the Auditor-General. The municipality has cooperated fully with the Office of the Public Protector, providing all requested information.
The municipality noted that it is nearing the completion and commissioning of nine boreholes, rejecting the conclusion that it would be expending one million rands per borehole. As of December 31, 2024, the municipality reported a physical construction completion rate of 65%, which included the drilling and equipping of nine boreholes. It clarified that R2.9 million had been paid towards the project for physical construction and consulting fees, rather than the R4 million alleged in the article. The municipality emphasized that the Mafube Local Municipality, the project’s beneficiary, operates on a cost-reimbursement basis, with all expenditures ratified by the Municipal Infrastructure Support Agency (MISA) before any payment can be processed.
In response to allegations against Municipal Manager Sipho Thomas that a borehole was illegally drilled on his private property in Parys, the municipality categorically denied these claims, describing them as attempts to tarnish his reputation and that of the municipality. It asserted that Thomas has diligently executed his obligations in relation to the borehole project in accordance with municipal supply chain management processes.
The municipality further stated that it views the borehole project as a reflection of its commitment to effectively manage the Municipal Infrastructure Grant (MIG) on behalf of the Mafube Local Municipality, aiming to address the water challenges faced by residents.