By Staff Writer: A ceiling collapse at Dingamazi Primary School has left 12 Grade 3 learners injured, prompting urgent calls for better oversight of school infrastructure projects. The incident occurred on Monday, shortly after the school’s recent renovations, raising serious concerns about the quality of workmanship and monitoring of government contractors.
Traditional leader Hosi Maswanganyi visited the affected school on the day of the incident, expressing sympathy and concern for the young students and the community. “This is a government institution, the Department of Education must ensure contractors are closely monitored to guarantee quality workmanship,” Maswanganyi emphasized during his visit, underscoring the importance of accountability in public projects.
The incident was detailed by Tsakani Macevele, a member of the School Governing Body (SGB), who voiced her frustration and disappointment. “As parents and members of the Dingamazi community, we are deeply concerned about what transpired. Several children are going to miss classes due to an incident that could have been prevented,” she stated. “We call on the Department of Education to ensure such incidents never happen again by properly monitoring ongoing upgrades.”
Macevele further highlighted the timeline of the failure, noting, “It hasn’t been long since this block was renovated, yet everything began to collapse shortly after the contractors left. It started with the veranda ceiling, and a few days later, the Grade 3 classroom incident occurred.”
School principal Martin Mathebula provided a detailed account of the events leading up to and during the collapse. He explained that the ceiling fell shortly after the children returned from their first break at 10:00 am. “I heard screams coming from the Grade 3 classroom around 11:00. From my office, I saw a blood-drenched child being brought to my attention. His scalp was badly cut, and we had to bandage him quickly before rushing him and the other children to hospital. Nine learners sustained minor injuries, while three suffered serious injuries,” Mathebula recounted.
He added that all injured students were treated and released to their parents by the end of the day, around 21:00. An inspection by experts revealed that the ceiling had fallen because it was not properly secured, with the use of incorrect nails being identified as a likely cause. “The contractor, however, claimed the collapse might have been caused by external factors, such as bats,” Mathebula said, dismissing the explanation as implausible.
Community members and school officials strongly disagreed with the contractor’s assertion, asserting that bats could not have caused a recently installed ceiling to fall. “It is clear that the wrong materials were used to secure it,” Mathebula asserted during the visit by Hosi Maswanganyi.
The incident has sparked widespread concern about the standards of construction and supervision of government-funded projects. Maswanganyi reiterated the need for strict quality control, emphasizing that “the Department of Education must ensure contractors are closely monitored to guarantee quality workmanship.”
Meanwhile, education spokesperson Mike Maringa confirmed that investigations into the incident are ongoing. “We will decide on the appropriate action once the report is ready. The part that collapsed is in a block that was recently renovated,” he said, promising to address the matter with the necessary urgency.