Court Blow Forces SANRAL to Change How It Awards Road Contracts

4 Mins Read
Email :

News/04 August 2026,08:00am/ Linda Mgomezulu

By Linda Mgomezulu: SANRAL is abandoning its controversial contractor-panel system for routine road maintenance, following a High Court judgment that found the procurement process “unconstitutional and unlawful”.

The decision marks a significant change in strategy for the South African National Roads Agency, which has faced a growing wave of legal challenges over its tender processes, record-keeping and procurement practices.

The Gauteng High Court in Pretoria set aside SANRAL’s decision to appoint a panel of 20 companies to carry out Routine Road Maintenance (RRM) work. The judgment followed separate legal applications by BCB Solutions and Botle Ba Afrika Roads, both of which had sought information about the tender after failing to secure contracts.

The value of the tender has not been disclosed.

The judgment sharply criticised SANRAL’s handling of documents linked to the tender. The agency had been ordered by two judges to provide information within a specified period, but the court found that its response fell well short of what was required.

Although SANRAL eventually supplied some documents, they were described as “disorganised, incomplete, partially inaccessible, and materially deficient,” according to the applicants’ submissions quoted in the ruling.

The applicants also complained that important records were missing and that sections of the documents had been redacted without explanation.

“The applicants also say that a significant number of these documents was missing and portions of some of them were redacted without an explanation. There is no need for the redaction of any part of the documents as no confidential price information is included in the bid documents,” the judge wrote.

The court also found shortcomings in the way the tender committee recorded its deliberations. Instead of keeping detailed minutes showing how members debated individual bidders, the committee recorded only the final decisions.

The judge said the committee “did not keep full minutes of their meetings reflecting deliberations which took place before voting on resolutions, including to appoint or disqualify a particular bidder in the tender. They only recorded the bare resolutions taken”.

The ruling added a further note of concern: “One can only hope – which hope I still arrived at grudgingly – that this type of incidents were [sic] few and isolated”.

The judgment has already triggered a major overhaul of SANRAL’s procurement approach.

According to SAnews, SANRAL chief executive Reginald Demana said the agency would scrap the panel model for routine road maintenance and engineering consultancy services. The organisation will instead return to the traditional open-tender system.

Demana was quoted as saying that no additional work could be allocated through the panel contracts following the court ruling. To prevent disruptions on the country’s roads, new tenders will be advertised in phases.

SANRAL said it would consult affected bidders about the consequences of the judgment. The agency also planned a media briefing to respond to allegations involving corruption, procurement failures, litigation and internal weaknesses.

Demana reportedly said SANRAL had “learned important lessons” from the court battles and admitted that the agency had underestimated the complexity of introducing the panel procurement model.

The return to open tenders, he said, would strengthen transparency while allowing maintenance of the national road network to continue.

The RRM ruling is the latest development in months of litigation involving SANRAL’s procurement processes.

In a separate High Court case in June, technology company WIB Intellitech unsuccessfully sought an urgent interdict to stop the implementation of an information technology contract awarded by SANRAL.

Although the court dismissed the application on procedural grounds, the case raised questions about a contract allegedly worth R438.3 million. WIB claimed SANRAL had awarded the tender despite a competing bid of approximately R101.2 million — allegations the agency disputed.

“The irreparable harm raised by WIB is that SANRAL has allowed Zimele to commence work in terms of the contract despite the award not having been made viewable on the website of SANRAL,” the ruling reads.