Free State

Dihlabeng Mayor James Tseki Tables R1.32 Billion Budget to Tackle Water, Roads and Housing Crisis

5 Mins Read
Email :

Free State/31 May 2026, 11:47am/ GoodWill Mathebula

Tseki James Tseki: Image Supplied

By GoodWill Mathebula: Dihlabeng Municipality has unveiled an ambitious R1.32 billion budget for the 2026/2027 financial year, with Executive Mayor Clr Tseki James Tseki placing service delivery at the centre of his administration’s plans.

Tabling the budget, Tseki said the municipality projects total revenue of R1.320 billion against expenditure of R1.317 billion, leaving an operating surplus of R2.5 million. The municipality has also set aside a strong capital budget of R268 million, a sharp increase of R98 million from the original R169 million, representing a 58% rise for the 2026/2027 financial year.

The mayor presented the budget as both a financial and political statement, arguing that local economic progress depends on clear political direction and stronger support from provincial and national government.

“We cannot separate politics from the economy,” Tseki said, stressing that Dihlabeng’s recovery and development would require both financial resources and professional expertise from higher levels of government.

At the heart of the budget speech was a bold promise: service delivery comes first.

The municipality plans to intensify efforts in water and sanitation, including the refurbishment of aging pipes, improved water distribution channels to households and businesses, and the incorporation of proposals from communities and institutions.

Electricity access also featured prominently, with the mayor saying the municipality would revisit its indigent programme to ensure poor households are not left behind, while engaging Eskom on ways to make power more affordable and accessible.

Housing remains another major focus area. Tseki pledged to tackle the backlog in housing provision, continue issuing title deeds, and work towards the eradication of slums and informal settlements. At the same time, the municipality is promising renewed attention to roads and infrastructure, especially in neglected communities.

In one of the strongest sections of his speech, the mayor took aim at the repeated patching of damaged roads, saying the current approach is no longer working.

Dihlabeng, he said, wants to move away from temporary repairs using cold asphalt and instead pursue durable, sustainable road reconstruction, guided by engineers and road construction specialists. In some areas, the municipality is even considering paved inner roads, which are viewed as better suited to local traffic conditions.

Beyond bricks and mortar, Tseki also used the budget speech to focus on the social fabric of the municipality.

He committed the municipality to improving staffing and administration by ensuring qualified and committed people are employed in strategic service delivery positions.

He also highlighted plans to invest in the wellbeing of children and young people through sport, recreation and anti-drug campaigns.

The mayor said idle youth are vulnerable to drug abuse and anti-social behaviour, and vowed to expand sporting grounds, upgrade playgrounds, swimming pools and indoor facilities, and strengthen school visits aimed at addressing bullying, harassment and substance abuse.

He called for partnerships with parents, teachers, churches, NGOs and community-based organisations to help rebuild disciplined and empowered communities.

The budget speech was also used to showcase what the municipality says it has already achieved.

In housing, Dihlabeng says it issued 1,568 title deeds in the past financial year, handed out 1,970 residential sites, and allocated 690 RDP houses in partnership with the Department of Human Settlements, with 100 already completed.

An additional eight sites were allocated to military veterans in Bethlehem. The municipality also reported that its Municipal Planning Tribunal approved 20 development applications, aimed at promoting orderly planning.

On technical services, the municipality said it completed 100% of scheduled work to upgrade and refurbish drainage systems, stormwater channels and raw water pumps across Bethlehem, Fouriesburg, Rosendal, Paul Roux and Clarens.

Water and sanitation projects completed or advanced during 2025/26 include the upgrading of Clarens Water Treatment Works, refurbishment of inlet works at Bohlokong wastewater treatment works, upgrades at Saulspoort Water Treatment Works, replacement of asbestos pipelines, filter automation, and the drilling and equipping of boreholes in Clarens and Fouriesburg.

Several major water projects are also under construction, including:

Construction of two 630mm steel bulk pipelines, each 3.2km long, from Saulspoort Water Treatment Works to Birdcage Hill Reservoir, currently at **38% progress.

Upgrading of Caledonspoort raw water abstraction point, also at **38% progress.

Upgrading of Saulspoort Water Treatment Works Section C, at **98% progress.

Upgrading of Saulspoort Section E, increasing capacity from **40Ml to 60Ml per day, at 43% progress.

Clarens/Kgubetswana raw water pump station upgrades, at **92% progress.

For the 2026/27 financial year, Dihlabeng has secured a major R200 million allocation from the Regional Bulk Infrastructure Grant (RBIG) to confront its water challenges. That funding will go towards completing the Saulspoort capacity upgrade and the construction of the two steel bulk pipelines.

An additional R25 million from the Water Services Infrastructure Grant (WSIG) will fund the upgrading of the Caledonspoort raw water abstraction point and the Mashaeng wastewater treatment works, which will be expanded from 1.125 ML/D to 2.2 ML/D.

On roads and municipal infrastructure, the municipality has also received R35 million from the Municipal Infrastructure Grant (MIG). The projects planned under this grant include:

Construction of a 1.2km block-paved road and stormwater channels in Mashaeng, Fouriesburg.

Resealing of 2.5km of road with hot asphalt** in Bohlokong’s Bakenpark.

Procurement of specialised waste management vehicles for all towns.

Phase 2 upgrading of the Bakenpark swimming pool** in Bohlokong, Bethlehem.

The municipality also listed a string of completed road achievements in 2025/26, including road upgrades in Bohlokong, Bethlehem, Fouriesburg, Baken Park, Mashaeng and Rosendal/Metati. Among these were the upgrading of 9th Avenue, rehabilitation of Old Lomond Street, repairs to key intersections in Bethlehem, and the paving of roads in Rosendal/Metati.

Projects still under construction include the resealing of Baartman and La Provence streets in La Provence/Jordania, currently at 60% progress, the upgrading of streets in Bersig at 37% progress, and the resurfacing of roads in Mashaeng at 73% progress.