By Staff Writer: In a briefing held at Riverlands near Malmesbury in the Western Cape, the Minister of Water and Sanitation, Pemmy Majodina, presented the preliminary findings on the dam failures in the region.
On August 8, extensive flooding caused significant damage to properties and infrastructure, leading to the provision of humanitarian assistance to the affected communities.
Majodina reported that three dams located on Dassenberg Farm, which falls under the jurisdiction of the City of Cape Town, had breached. The flooding impacted the downstream community of Riverlands in the Swartland Municipal area.
“These dams had no names or their names were not known. We came to refer to them as dam one, two, and three, starting from the downstream dam. All of them did not have adequate spillways and initial information suggested that dam three filled beyond the safe level, resulting in overtopping due to high rainfall and associated run-off, causing dams two and one to fail in series,” Majodina explained.
She further stated that a dam engineer was appointed by the City of Cape Town to assess the damage, and they found that a fourth dam also had insufficient spillway capacity. The City then constructed a spillway for the fourth dam on August 10, 2024, after receiving permission from the department.
On August 11, Majodina initiated an investigation to determine the causes of the dam failures, verify dam safety compliance, and establish ownership. The investigation team was given seven days to complete its work.
“On August 12, our dam safety team began with the investigation in Riverlands. On arrival, our team discovered that dam four, which is the highest dam in the valley, was on the verge of failure. To reduce the risk of potential failure, our Dam Safety Office took the decision to partially empty the dam to protect the lives of the community members living downstream. Furthermore, the team discovered another dam downstream of dam one, which we call dam zero,” Majodina said.
The preliminary report, handed to Majodina on August 26, revealed that dam three was constructed between 1960 and 1966, while dams one and two were built between 1966 and 1992. Dam four, the largest, was constructed between 2000 and 2005, and it appears dam zero was built around the same time.
The report also uncovered that the property was once privately owned but was acquired by the national government in 2019, with the Department of Agriculture, Land Reform, and Rural Development becoming the custodian.
Majodina emphasized that under the National Water Act, the current owner, the Department of Land Reform and Rural Development, had the responsibility to register the dams as having a safety risk within 120 days, which was not done. Previous owners also failed to comply with this requirement.
She also clarified that although the dams were not constructed by the government, it was the owner’s responsibility to ensure they complied with relevant legislation. The dams were not registered with the Dam Safety Office, as required by law.
The investigation found that dam three failed due to internal erosion, leading to a domino effect on the downstream dams. The lack of proper spillway structures meant the dams did not meet safety standards, which could have been avoided had the dams been registered and evaluated by a qualified dam engineer.
Additionally, no licenses were issued for the construction of any dams on the property, as required by the Water Act.
“The department will take action against the owner of the dams for non-compliance with the Act and associated regulations. The action will include relief for financial compensation for damage to infrastructure. Criminal investigations are ongoing and will focus on current and past owners that constructed and operated the dam in non-compliance with water use authorisation and dam safety requirements,” Majodina said.
She also mentioned that the current landowners must submit a rehabilitation plan for the affected areas and engage with the Swartland Local Municipality to assess the extent of the damages. Should they decide to rebuild the dams, they must apply for a water-use license and dam safety license from the Department of Water and Sanitation.