Mangaung City Manager Sello More Says Freedom Square Sewage Crisis Will Be Fixed by December 2026

5 Mins Read
Email :

Free State/23 October 2026, 05:08am/ Linda Mgomezulu

Sello More: Image Supplied

By Linda Mgomezulu: Mangaung Metro has moved to reassure Freedom Square residents that the sewage-filled streets and damaged roads captured in recent television footage are not being ignored — but are instead the painful middle stage of an extensive repair project expected to be completed by December.

City Manager Sello More, speaking during a live interview on Newzroom Afrika, said the work in the area is being funded through National Treasury and is intended to address years of failing sanitation infrastructure in the informal settlement.

More requested an opportunity to respond to the footage, arguing that the scenes of sewage flowing through the community must be viewed against the backdrop of a project already in progress.

“Okay Freedom Square actually is I think fortunately we can say that Freedom Square is an area of a live project,” More said.

“It’s something that has been identified not only by the citizens but also by a National Treasury as the councillor reflected. Funds have been channeled towards fixing the problems in Freedom Square.”

According to More, Freedom Square developed with limited basic services, leaving residents to endure longstanding sanitation failures. He said the municipality’s current intervention includes replacing pipes and installing manholes — work which, while disruptive, is designed to provide a lasting solution.

“You know that Freedom Square like all other informal settlements people settled. Possibly there was minimal in terms of services that were in the Freedom Square area. So why I’m saying is a live service delivery area. We are busy now fixing the pipes. Busy putting in manholes. So there is serious inconvenience.”

The City Manager did not dispute the seriousness of the problem, acknowledging that sewage overflows have been a reality in Freedom Square for several years.

“I think if you would have been there in the last three years or so there was sewage running all over the place.”

But he maintained that sewage may remain visible while construction continues, warning residents and observers that the work cannot eliminate the crisis overnight.

“So why we requested a right to reply on this matter is because whilst the work is being done, there is a likelihood that the sewage problem still persist. The project will finish around December. But we would have cleared everything that you would have seen.”

More said the municipality had not responded during the station’s earlier live coverage, but stressed that the City’s intervention is active and ongoing.

“I just wanted to say that we did not respond to the live coverage of your TV station. But it’s a project that is ongoing. Ja. It’s a live project. So there will be responses from time to time on some of the sewage but there is a project that is being implemented there to ensure that there is no sewage running in the area of Freedom Square of Mangaung.”

The programme also highlighted deep potholes and open trenches near the community soccer field, raising fresh safety concerns for residents — particularly children and pedestrians using the area.

More said the municipality had instructed its service provider to improve safety measures around active construction zones.

“There is massification of work in Freedom Square as I’ve reflected. I think you are correct. We have also raised the issues with the service provider to say that in areas where work is being done, please cordon off so that citizens can be safe,” he said.

He linked the damaged road surfaces directly to the persistent sewage leaks, saying wastewater had weakened and destroyed infrastructure beneath and above ground.

“I must just point out what you are seeing there as massive potholes. It’s as a result of the sewage that is running all over the place. You know that sewage has also capacity to destroy all the entire infrastructure.”

More said the municipality had chosen to prioritise the underground sewer network before spending money on road repairs — a decision aimed at preventing newly repaired roads from being damaged again.

“So as we came in as a new administration we said that let first fix the sewage because you can’t fix the roads when the sewage is busy actually eating the same roads. So we are fixing the sewage there.”

Once the sewer upgrades have been completed, the municipality plans to assess the damage to roads and other public infrastructure, he said.

“Of course the next step will be to see what infrastructure has been damaged. What can be done now to enhance other infrastructure. In particular the road infrastructure.”

“If you repair it now is the same. So we’re anticipating that by December we’d have finished with the issue of sewage and the issue of pipelines that we are re-establishing there.”

For Freedom Square residents, the December deadline now stands as the City’s central promise: that the sewage running through their streets will finally be brought under control, clearing the way for safer roads, restored public spaces and a more dignified living environment.